Dandot Cement Co Ltd in Punjab, Pakistan is expected to resume commercial production in the first quarter of the next financial year after completing Balancing the Modernisation of Replacements (BMR) at its Jehlum cement plant. The BMR project aims to meet legal standards and avoid adverse action from the Environmental Department. Progress has been made on mechanical and civil works, steel structure fabrication, and refractory work. The administration has invested PKR2.972bn to date for BMR, including PKR555m during the last quarter. A 5MW solar power plant has been constructed, and electricity load enhancement has been approved. The company is expected to attain production efficiencies for long-term financial viability with environmental compliance after the BMR project.